Daily inspection of concrete mixing plant

Post time: 2020-03-27 10:45 Post category:

Concrete mixing plant is a machine that mixes cement, sand aggregate and water and mixes them into a concrete mixture. In order to make better use of concrete mixing plant , we should do the following.

  1. Check the working conditions of the lubrication points of each rotating part every day, and replenish the lubricant in time.
  2. Check the amount of lubricating oil in the lubricating oil cup of the blender daily and replenish the lubricating oil in time.
  3. Check the oil level of the oil mister on the air system once a week. Use a lubricant with a viscosity of 2.5 to 7 ° E.
  4. Open the drain valve once a day before starting and after turning off. Drain the condensed water from the air compressor and the air tank.
  5. Check fasteners such as bolts and nuts for looseness every week. When looseness is found, it must be tightened in time, especially some parts subject to variable amplitude load.
  6. Check the equipment of the water supply, gas supply and admixture system regularly every day.
  7. Check whether the electrical control system and various instruments are normal every day.
  8. Check whether the mixing shaft and the whole of the mixer are clean daily. If there is too much concrete on the mixing shaft, it must be manually cleaned.
  9. Clean or replace the filter in the dust collector of the powder tank every six months. When cleaning the filter in the dust collector of the powder tank, do not wash it with water, only use air blow or soft brush to clean it.
  10. If the downtime exceeds one week, the materials in each measuring bucket must be emptied. Such as cement, water, additives and various aggregates.